The short version
Bradley is building a Mattel Wonder Indoor Waterpark, one of four Mattel has confirmed in the U.S. Its cost is now reported at upward of $150 million, up from first estimates of $75 million to $80 million.
The waterpark covers two-plus acres under a retractable glass enclosure, so it can run year-round, on a site of roughly 30 acres southeast of Northfield Square Mall.
Two construction contracts have been awarded: $2.9 million to Tenco Excavating of Manteno and $1.55 million to Abbey Construction of Aurora. On Nov. 16 the board added $5.9 million for a construction manager, Arco/Murray National, and $9.9 million for a 30,000-square-foot wave pool.
An invitation-only "Construction Party Kick-Off" is set for Tuesday, Dec. 8, in place of a groundbreaking.
Opening: late 2028 or early 2029, if all goes as planned.
Latest updates
- Nov. 21, 2026 · The BourbsArizona just got a Barbie Hotel. Bradley is about to pick a hotel for its Mattel waterpark. Could ours be themed too?
Mattel's first themed hotels are going up in Glendale, Ariz. Bradley's mayor says the village aims to pick a hotel operator for its waterpark in about three months. Nobody has said Bradley's will be Mattel-themed, but here is how Arizona got there and what it would take here.
- Nov. 20, 2026 · The BourbsGreeley makes the end of its Catalyst deal official, 7-0, and says it still holds an option on a Mattel-themed water park
The Colorado city that once planned a Mattel water park voted to document the end of its developer agreement. Its resolution says the city's option on the Mattel park runs to May 31, 2027.
- Nov. 20, 2026 · The BourbsMattel's Arizona theme park gets a new name, a Barbie Hotel and bigger plans, but still no opening date
Mattel Adventure Park in Glendale, Ariz. is now Mattel City. It's a separate venture from the Mattel Wonder waterpark program, which includes Bradley's.
- Nov. 20, 2026 · The BourbsThe first Mattel Wonder waterpark, in Bellevue, Neb., has its exterior and retractable roof finished
Bellevue is Bradley's sister park and is planned to open first, at the end of 2027.
- Nov. 20, 2026 · The BourbsKansas City-area Mattel Adventure Park clears a planning step; council takes it up Dec. 21
Bonner Springs planners advanced the land plat for the 180-acre district. It's a separate Mattel theme park, not a Wonder waterpark.
- Nov. 20, 2026 · The BourbsThe company that says it will run the Mattel Wonder waterparks has a new president
American Resort Management named Marshall Myrman president and promoted Justin Brown, who was at Bradley's Mattel vote last December, to chief operating officer.
- Nov. 20, 2026 · The BourbsMattel's new president and COO will also oversee the business behind its waterparks
Steve Totzke became President and Chief Operating Officer on Nov. 11, overseeing consumer products and experiences among other areas.
- Nov. 17, 2026 · BradleyWaterpark.comCost now upward of $150 million; $5.9 million construction manager and $9.9 million wave pool phase approved
Arco/Murray National of Downers Grove will manage the roughly two-year build. The deep dive and what the new cost means for residents.
- Nov. 17, 2026 · The BourbsBradley's Mattel waterpark now tops $150 million, report says; board hires construction manager, adds wave pool phase
Trustees unanimously approved $5.9 million for Arco/Murray National to run construction and also approved $9.9 million with OpenAire for a 30,000-square-foot wave pool phase.
- Oct. 27, 2026 · BradleyWaterpark.comDec. 8 kickoff party replaces the groundbreaking; $1.55 million paving contract approved 5-0
An invitation-only Construction Party Kick-Off at Plate'D Social, and construction contract No. 2 goes to Abbey Construction of Aurora.
- Oct. 13, 2026 · BradleyWaterpark.comFirst construction contract: nearly $2.9 million to Tenco Excavating
The first contract tied to actual construction of the waterpark, for site infrastructure.
- Oct. 1, 2026 · BradleyWaterpark.comMattel's new waterpark concept art: Barbie surf, a Hot Wheels tower, and Bellevue goes first
Mattel confirmed four sites, including Bradley, and showed what its Bellevue, Neb. park will look like.
What's inside a Mattel waterpark
On Oct. 1, 2026, Mattel released new concept art for its Wonder waterparks. It shows the park in Bellevue, Neb., which Mattel says is planned to open first, at the end of 2027. Bradley's final design has not been released, so Bradley's park could look different.




Concept art ©2026 Mattel. These show the Bellevue, Neb. park, not Bradley.
Bradley's park by the numbers
| Project cost | Upward of $150 million (first estimates: $75 million to $80 million) |
| Indoor area | About 160,000 sq ft, 105,000 of it water attractions |
| Waterpark footprint | Two-plus acres |
| Whole site | About 30 acres, southeast of Northfield Square Mall |
| Capacity | 1,700 to 2,000 people at a time |
| Projected visitors, year 1 | 411,000 |
| Projected visitors, year 10 | About 480,000 a year |
| WhiteWater West package | $20 million |
| Retractable glass enclosure (OpenAire) | $10.5 million |
| Wave pool, 30,000 sq ft (OpenAire) | $9.9 million |
| Construction manager (Arco/Murray National) | $5.9 million |
| Mattel license | 10 years, approved Dec. 8, 2025 |
Timeline
| Date | What happened |
|---|---|
| Dec. 8, 2025 | Bradley's Village Board approves the Mattel licensing agreement. |
| Oct. 1, 2026 | Mattel releases new concept art (Bellevue park) and confirms four sites, including Bradley. |
| Oct. 12, 2026 | First construction contract: $2.9 million to Tenco Excavating of Manteno for waterpark infrastructure. |
| Oct. 26, 2026 | Second contract: $1.55 million to Abbey Construction of Aurora for concrete and paving, approved 5-0. |
| Nov. 16, 2026 | Special meeting: $5.9 million construction-manager contract with Arco/Murray National and $9.9 million wave pool with OpenAire, both approved unanimously. Cost reported at upward of $150 million. |
| Dec. 8, 2026 | Invitation-only Construction Party Kick-Off at Plate'D Social in the Bradley 315 Sports Park, held instead of a traditional groundbreaking because of the time of year and the chance of winter weather. Officials say more specific designs will be unveiled then. |
| Late 2028 or early 2029 | Opening, if all goes as planned. |
The other Mattel Wonder waterparks
Mattel's Oct. 1 announcement confirmed four of five planned sites: Bellevue, Neb. (first, planned for the end of 2027), Orlando, Fla., Bradley, Ill. and Roanoke Rapids, N.C. Mattel has not named the fifth. Bellevue's park is about 100,000 square feet.
Not the same thing: Mattel Adventure Park in Glendale, Ariz. is a separate indoor/outdoor amusement park project, not a waterpark. Bradley's is a Mattel Wonder Indoor Waterpark.
What we don't know yet
- What Bradley's park will look like. Mattel's concept art so far is for Bellevue.
- Which Mattel brands Bradley's park will feature.
- Ticket prices and an exact opening date.
When any of that is announced, it will be here first. Our sister site, BradleyWaterpark.com, tracks every contract, vote and document in depth.
Waterpark Watch: the video series
- Episode 1What's inside a Mattel waterpark (coming soon)
- Episode 2Bradley's waterpark by the numbers (coming soon)
- Episode 3Bradley vs. the other Mattel waterparks (coming soon)
- Episode 4One year to the day (coming soon)
Want every update first?
Sources
- Daily Journal, "Downers Grove firm to oversee Bradley waterpark project," Nov. 17, 2026
- Mattel, "Mattel Unveils First Mattel Wonder Indoor Waterpark, Opening in Bellevue, Nebraska," Business Wire, Oct. 1, 2026
- Daily Journal, "Mattel waterpark kickoff event set; second construction pact awarded," Oct. 27, 2026
- Daily Journal, "Bradley awards $2.9 million construction contract for waterpark infrastructure," Oct. 13, 2026
- Daily Journal, "Looking ahead to what's in store for Kankakee County in 2026," Jan. 7, 2026
- Coaster101, "More Ways To Play: Mattel Splashes into Indoor Waterparks," Dec. 11, 2025
- BradleyWaterpark.com news